IBM-Texas agree to disagree over $863 million contract
Looking to avoid what would have been a costly and likely lengthy court battle IBM and the state of Texas’s Department of Information Services have apparently agreed to disagree over a failed $863 million data center consolidation pact.
Published reports, including this one from Statesman.com, indicate that under an agreement, IBM will transfer $20 million worth of equipment already installed to the state and forgo $26 million worth of billing for work it has already done. For its part, Texas will pay in total about $35 million owed to IBM for the cost of services and equipment. As of February, Texas had paid IBM almost $758 million and assessed the Big Blue $10 million in penalties for failing to meet certain contract requirements.
In other news: 12 seriously cool “toys” for big boys and girls
The original contract, signed in 2006, called for IBM to consolidate the state’s IT operations as well as reduce the number of data centers from 31 to two and provide specific services. At the time Texas said it expected the project to save it $179 million over the seven-year contract time-frame.
Problems surfaced in 2010 with Texas complaining IBM had fallen behind on the project and IBM saying disputing any snags.
In the end Texas Rep. John Otto, R-Dayton, told the Statesman.com, “What we had was not working, so we obviously needed to conclude the agreement we had and try to get out of it with as little litigation as possible.”
More: Advanced tech conflict: China’s rare earth stranglehold
For its part IBM said: “IBM is pleased an amicable resolution concerning the Data Center Services contract with the Department of Information Resources that recognizes the contractual rights of both parties has been reached. IBM will continue to work with DIR to successfully transition the project,” IBM spokesman Jeff Tieszen told the Statesman.com.
In the meantime Texas has indeed moved on, this week announcing its had given Xerox an $848 million, eight-year contract to do basically what IBM was to have done – consolidate 28 data centers into two. In addition IT services form Capgemini, got a six-year year, $127 million contract to oversee the consolidation project and operations, according to the Texas Department of Information Services.
Follow Michael Cooney on Twitter: nwwlayer8 and on Facebook
Layer 8 Extra
Check out these other hot stories:
Secret Service takes out “astonishing” cyber theft ring
Navy, Army open labs looking for robot, energy, fuel, mechanical inventions
Ambitious Army project takes Arlington National Cemetery high-tech
How to attract the military’s rapt attention: Sell fake service-related documentation on the Internet
CIA director tells a funny computer engineering joke
FTC goes after deceptive online car loan payoff ads
NASA, General Motors team to build robotic glove for human hands
US military shows off non-lethal heat-beam for crowd control
DARPA wants on-demand satellite imagery for smartphones
Know your rights: Identity theft victims express problems with reporting system
Lockheed: Prototype Space Fence tracking orbital debris
NASA looking for Star Trek-like Tricorder to track astronaut health
FAA wants public feedback on unmanned aircraft test sites
NASA, Rovio take Angry Birds battle into space